In the past week, there have been several questions raised about the cost of the Northern Pass project and who is poised to pick up the cost once it’s completed. It also led to some public scuffles in the media between Hydro-Québec (HQ) and its New Hampshire partner, Eversource.

On Thursday, both companies said they remain committed to the $1.6 billion project to transport 1,090 megawatts of electricity to New England from Canada to Deerfield through 192 miles of hydroelectric power lines.

“Eversource and Hydro-Québec have had a long-standing partnership to develop a transmission project that would deliver much-needed clean hydropower from Québec to New England energy consumers,” according to a statement from Eversource.

But just one day prior, in three Le Journal de Québec articles, it appeared that HQ was reassessing its financial arrangement with Eversource. One article claimed HQ would pay to bury about 60 miles of the line, mostly through the White Mountain National Forest, but refused to bury about 11 miles of the line in Canada, despite pleas from local residents.

A second article stated that HQ has assumed the risks of the project and would have to pay the entire cost. Yet, a HQ official claimed New England consumers would ultimately pay for the $500 million additional cost for burying the lines and the entire Northern Pass project — a private transmission line for the exclusive use of HQ.

The third article suggested that HQ was considering abandoning the project if it wouldn’t be profitable for Québec residents. HQ is a crown corporation, meaning it’s a business essentially owned by the Province of Québec.

On March 8, HQ spokesman Serge Abergel told 98.5 FM that his company “will not pay a penny to build the line in the United States.” He argued that Hydro-Québec wanted “the transportation costs to be borne by the American customer and that’s what the partner Eversource says too.”

But in the Northern Pass statement, the company reiterated that the cost of the project will not fall on New Hampshire customers.

“Northern Pass Transmission, an Eversource subsidiary, will finance and build Northern Pass, the U.S. portion of the transmission project,” Eversource said in a statement. “Hydro-Québec will do the same for the Canadian portion of the project. The cost of Northern Pass will be recovered through use of the transmission line for delivery of energy to New England.”

Both companies said they are also working on a proposal to supply hydropower from Québec, using the Northern Pass transmission line, to Massachusetts. Proposals are expected to be submitted to the Commonwealth in the spring.

“We firmly believe in the strength of our alliance with our American partner, Eversource,” Hydro-Québec said in a statement.

What led to this very public skirmish between the two entities? It could have to do with the fact that HQ and Eversource may not have renewed its Transmission Service Agreement (TSA) with the Federal Energy Regulatory Commission (FERC).

The TSA the companies filed in 2010 states that HQ would reimburse Eversource for all development costs. In December 2013, Eversource requested an amendment to their 2011 TSA noting delays in the project and wanting to change the term “third anniversary” with the term “approval deadline,” which they set as Feb. 14, 2017 or another date both parties mutually agree to in writing.

Spokespersons at the FERC said that to date there is no signed and renewed TSA between Eversource and HQ on file, according to a report from the Caledonian Record. Eversource also declined to say if they had a renewed TSA with HQ, what the terms were, and if it would present it to investors.

The TSA is important because it outlines how Eversouce is expected to be paid to build the Northern Pass line.

The Society for the Protection of New Hampshire Forests sent a letter to U.S. Sen. Jeanne Shaheen on Tuesday, asking her to make inquires at the FERC about the status of the TSA between Eversource and HQ:

“Northern Pass has repeatedly argued that New Hampshire ratepayers are not paying for the construction  costs of their project,” the letter states. “They repeatedly cite the TSA as the basis for their claim that Hydro-Québec is paying for the construction of the transmission line. The SEC [Site Evaluation Committee] and interveners in the upcoming adjudicatory hearing cannot fully address the economic issues of impact — or whether the project is in the public interest — without the information provided by the TSA affirming that there is in fact a legally binding agreement between the two parties to this project.”

Hearings are expected to begin on the Northern Pass project next month, which will help a subcommittee of the Site Evaluation Committee make the ultimate decision if the project will move forward or not by September 30.

While it appears the two companies have publicly reconciled their differences for now, Northern Pass project opponents are using the disagreement to reiterate their point that it’s likely Granite Staters, or even Bay Staters, will pick up the cost at some point if the project is completed.

“There’s no reason to believe them now about who will pay for Northern Pass,” said Judy Reardon, senior adviser of the group Protect the Granite State, in a statement. “You and I will pay the bill, but only if we allow Northern Pass to succeed.”

Those skeptical about the project also argue that the economic climate is changing for electric utilities, making the project less advantageous than when it was first proposed.

In 2011, when Northern Pass was first proposed, high natural gas prices drove electricity prices higher. However, those prices have dropped in recent years, and New England is currently seeing its lowest electricity costs in a decade.

According to a study released last week by the Carsey Center for Public Policy at the University of New Hampshire, the average residential electric bill in the state is the same as the national average, and the average commercial electric bill is actually lower than the national average.

People who support Northern Pass say it will create jobs, deliver cheap electricity to the New England market, and is a important long-term economic investment into keeping energy rates low for residents and businesses. Gov. Chris Sununu has been a longtime supporter of the Northern Pass project.

Follow Kyle on Twitter.

Sign up for NH Journal’s must-read morning political newsletter.